Feb 26 – Construction update

We’ve completed the piles and next up is the grade beams. We should have a structure in place by June.

We’re about 10 days into the process and we’ve only had one headache. I was told 2 days before they began piling that they needed water hooked up on the site. Normally that takes about 2 weeks. We didn’t have 2 weeks since the pile machine was already rented and only two exist on island. We had to pull some “west bay connections” and got a water guy in to connect the day they arrived. So far so good. I hired a construction manager to tend over the process so I can alleviate most stresses but I am expecting many!